DECEMBER 2015 - CURRENT WORK

DECEMBER 2015 - CURRENT WORK

DECEMBER_2015

SURFACE DRAINAGE: Work is approaching completion with only a few pits to be finished. This has been a huge job.
SEWERAGE LINES: Work is progressing well with more than 150 metres of trenching completed and pipe laid. After running of electrical conduit over the next week all trenches will be backfilled.
SEWERAGE SYSTEM: Secondary sewerage tank delivered and installed and absorption trenching complete.
WATER: Running of hot, cold and tank water lines to all wet areas


WORKS IN PLANNING
CLADDING: Cladding and fascia work to external areas
RENDERING: of existing blockwork
ELECTRICAL: preliminary design
MECHANICAL: preliminary design


SPECIAL THANKS:
Andrej
Branislav
Janko
Milan
Radovan
Milan Bajic
Ozren Coso
Dusan Cupic
Nenad Djogo
Dragan Djordjevic
Surveyor Dragan
Brane Gligoric
Dragan Ignjic
Bogdan Komatovic
Milos Komatovic
Bogomir Kuliza
Bobi Oliveric
Milan Pantelic
Miljan Pavlovic
Dejan Polumirac
Neven Pupovac
Fr Sasa Radoicic
Biljan Stankovic
Predrag Stankovic
Dragan Stegnjaic
Stevo Trifunovic
Miroslav Uzelac
Vele Kovacevic
Zoran Cupac
Fr Djuro Djurdjevic
Danny Jovanovic
Miroljub Mihaijlovic
Randon Ilic
St George Cabrammatta

 

 

DECEMBER 2015 - CURRENT WORK